The Correct Order of Trades in a Renovation — Why Sequence Matters

There is a sequence to renovation work that isn’t arbitrary or a matter of preference. It’s the sequence that exists because the work of one trade creates the conditions that the next trade needs. When that sequence is violated — because of poor planning, because a trade was available at the wrong time, or because the renovation company isn’t managing the coordination — the results are expensive.

The most common example: the waterproofing is tiled over before the mandatory inspection is carried out. The tiler was available and the schedule was behind. The waterproofing passes inspection, the build continues — but if the waterproofing had failed, the tiles would need to come off.

The correct answer is: the tiler waits. Always. This article explains the correct trade sequence for the most common Perth renovation types, why each step exists, and what the consequences are of getting it wrong.

The Correct Trade Sequence — Bathroom and Ensuite Renovation

A bathroom renovation involves more licensed trades than almost any other renovation type, and the sequence between them is the tightest. Here is the correct order, and why each step exists.

Stage

TradeWhy It Must Come Here

1

Strip-out and demolitionReveals what's actually there. Asbestos, galvanised pipes, and non-compliant wiring are identified before any new work proceeds. Scope changes happen here, not later.

2

Structural work (if required)Wall removal, new lintels, and structural modifications must be completed and inspected before the room can be closed in. Cannot be done after framing or linings are in

3

Rough-in plumbingPipes and drains are set in their new positions while the floor and walls are open. Slab cutting (if required) happens at this stage. Cannot be done after floor finishes are installed.

4

Rough-in electricalConduit, cables, and junction boxes are installed in the wall and ceiling cavity while open. Cannot be done cleanly after wall sheeting is installed.

5

Wall sheeting and substrate preparationWaterproof membranes and tile substrate (Villaboard, Hebel, or similar) are installed. Must come after rough-in services are in — and before waterproofing.

6

WaterproofingApplied to the substrate before tiling. THIS IS A HOLD POINT — waterproofing must be inspected and approved by a licensed inspector before any tiles are laid. Non-negotiable under AS 3740:2021.

7

Waterproofing inspectionA licensed waterproofing inspector or building surveyor inspects and approves the waterproofing membrane. Tiling cannot start until this is passed. If the building is under a building permit, the inspection is part of the permit conditions.

8

Tiling — floor and wallsAfter waterproofing is approved. Floor tiling sets the datum for vanity and toilet heights. Must be completed before cabinetry is installed.

9

Cabinetry and vanity installationCabinet maker arrives after tiling is complete. Vanity height, toilet rough-in height, and shower niche positions are all set against the finished tile floor.

10

Benchtop fabrication and installationStone or laminate benchtop is fabricated to the exact vanity dimensions. Cannot be templated before vanity is installed. Lead time for stone: 5–10 working days after template.

11

Plumbing fitoffTaps, toilet, shower fittings, and waste connections are completed by the licensed plumber after cabinetry and benchtop are installed. Fitting chrome against tile, not against a substrate.

12

Electrical fitoffLight fittings, exhaust fan, heat lamp, and safety switch are connected and tested by the licensed electrician. Certificate of Compliance issued.

13

Shower screen installationInstalled after tiling and plumbing fitoff. Glass is templated to the actual finished shower dimensions.

14

PaintingFinal trade. Painted after everything else is in — cabinetry, fittings, and screens are all in place. Painter does not return to touch up after other trades.

15

Silicon and sealantApplied last, after painting. Fresh silicon against a painted substrate. Silicon in grouting junctions and at the base of the shower screen.
Watch out — The waterproofing inspection (Stage 7) is the single most important hold point in a bathroom renovation. A renovation company that tiles before the inspection passes is either not obtaining the inspection, or has documented the inspection without a licensed inspector physically attending. Both are non-compliant. Both leave the homeowner with no warranty and potential liability for future water damage.

The Correct Trade Sequence — Kitchen Renovation

A kitchen renovation has a different sequencing logic to a bathroom — there is no mandatory waterproofing inspection, but the cabinetry lead time and the correct sequencing of electrical and plumbing work around it require careful management.

Stage

TradeWhy It Must Come Here

1

Strip-out and demolitionIncludes wall removal if open plan. Structural assessment and beam installation if load-bearing. Asbestos and services identified.

2

Structural work and wall framingNew walls, openings, and structural elements completed and inspected before closing in.

3

Rough-in plumbing Sink waste and water supply in new positions. Gas point if applicable. Must be done before wall sheeting.

4

Rough-in electrical Oven circuit (typically 20A), dishwasher circuit, under-cabinet lighting conduit, rangehood circuit. All in the wall cavity before sheeting.

5

Wall sheeting, plaster, and painting preparationWalls closed in. Plaster set and sanded. Painting commences on walls and ceiling — before cabinets arrive.

6

CABINETRY DELIVERY AND INSTALLATION — critical path itemCustom cabinetry typically has a 4–6 week manufacturing lead time from design approval. Everything else on the schedule is built around the cabinet delivery date. This is the longest single lead time in a kitchen renovation.

7

Benchtop templateStone benchtop templater visits the site with cabinets installed to take exact measurements. Lead time after template: 5–10 working days.

8

Benchtop installation Stone delivered and installed. Scribes to wall and adjacent surfaces completed at this visit.

9

Splashback tilingTiler installs splashback against finished benchtop. Requires the benchtop to be in place to ensure correct heights and setouts.

10

Plumbing fitoff Sink, tapware, and dishwasher connections after benchtop is installed. Compliance certificate issued.

11

Electrical fitoffAppliances connected, under-cabinet lighting installed, oven commissioned, safety switch tested. Compliance certificate issued.

12

Appliance installation and commissioningOven, cooktop, and rangehood installed and tested.

13

Final painting and touch-upTouch-up painting around cabinetry, handles, and any disturbed surfaces after all trades have finished.

House & Co note:

The cabinetry manufacturing lead time (Stage 6) is the critical path item in a kitchen renovation — not the on-site construction. A kitchen project that approves the design in early April with a 5-week manufacturing lead time cannot start cabinetry installation before mid-May, regardless of how quickly the other stages are completed. House & Co factors manufacturing lead times into every project schedule from the day of design approval.

What Goes Wrong When the Sequence Is Broken

GroupTiling before waterproofing inspection

The tiling looks correct from the surface. The waterproofing inspection is either not obtained or is backdated. Two years later, water penetrates through a failed membrane. The tiles on one wall need to come off, the membrane stripped, reapplied, inspected, and retiled. Cost: $8,000–$15,000 for a bathroom wall. The original “saving” on the inspection was negligible.

GroupCabinet installation before benchtop template

A benchtop fabricator templates the cabinet without the wall being truly plumb or the cabinets fully level. The template is made. The stone arrives and doesn’t fit because a 4mm discrepancy at one end of a 3-metre run was not caught. The stone goes back for refabrication. Project delayed 2 weeks. Remediation cost charged as a variation.

GroupPlumbing fitoff before tiling is complete

The plumber completes fitoff before the tiles are in. The waste outlet position is 12mm out from where the tiler needs it for the floor to drain correctly. The plumber returns. The junction is exposed. The tile is cut around a position that doesn’t work. The result is visible.

GroupPainting before all trades are done

The painter completes all work before the electrical fitoff. The electrician damages the ceiling cutting in a downlight that was not in the painting scope. The painter returns for a second visit. The second visit is not included in the quote.

Why This Is the Coordination Work That Matters

Every scenario above has the same cause: a renovation where the trades were not properly coordinated — where each trade arrived when they were available, not when they were needed. This is the operational work of renovation project management. It is invisible when it’s done correctly and very visible when it isn’t.
House & Co manages the trade sequence on every project. The project schedule is issued to every trade before work starts. Hold points are identified and communicated. Trades do not proceed past a hold point without sign-off. The result is not just a renovation that finishes faster — it’s a renovation where the work is done correctly the first time.

Related renovation services in Perth

House & Co manages every room under one agreement. Browse our other services below — all
spokes connect back to the same team, the same process, and the same fixed-scope quote.

Frame 53 (1)

Bathroom Renovations Perth

From $25,000
House & Co delivers kitchen renovations across Perth exact dimensions, stone benchtops, and all licensed trades under one agreement.
Frame 53 (2)

Kitchen Renovations Perth

From $30,000
House & Co delivers kitchen renovations across Perth exact dimensions, stone benchtops, and all licensed trades under one agreement.
Frame 53 (3)

Laundry Renovations Perth

From $20,000
House & Co laundry renovations include custom ceiling-height cabinetry, new floor and wall tiling, sink and tapware.
Frame 53 (4)

Ensuite Renovations Perth

From $20,000
House & Co delivers Ensuite renovations across Perth as our main bathroom renovations, applied to the space that starts and ends your day.
Frame 53 (5)

Alfresco Renovations Perth

From $15,000
Perth’s climate makes the alfresco one of the most-used spaces in any home. House & Co renovates alfresco areas across Perth
Frame 53

Home Extensions Perth

From $80,000
House & Co builds home extensions across Perth granny flats and room additions, all with full permit management and every licensed

Questions about your renovation? Talk to House & Co.

Free in-home consultation. Fixed-scope quote. No obligation.