Full House Renovation — Dianella

A generous Dianella home with a pool, a large kitchen, and a project that ran twelve months instead of four. The result was worth the wait — and the reasons it took longer are worth understanding before you start your own renovation.

The Brief

The owner had purchased this Dianella property with a clear objective: renovate it fully and then move in. It was a generous home — larger than the average Perth renovation project, with a substantial kitchen and open-plan dining area, a large living room that needed structural work to open it up properly, an alfresco and pool area that had been left to deteriorate, and a scope of work that touched virtually every room in the house.

The property was clean in all the ways that matter most. No asbestos was identified in the wall linings or ceiling surfaces. No galvanised supply pipes were found. The electrical installation was assessed and found to be compliant throughout. No lead paint was identified. For a Dianella home of this era and scale, a clean structural and services baseline meant the renovation could proceed without the additional cost and timeline impact of hidden works remediation.

The brief was contemporary throughout — the gold-and-dark kitchen palette seen in the before photographs gives some indication of the direction the client was heading. The herringbone timber floor running from kitchen through living through to the alfresco deck was the single most important design decision, creating visual continuity through what is effectively a large open-plan family home.

Before Photographs

What We Did

Kitchen & Open-Plan Dining

  • Full strip-out of existing kitchen — honey pine cabinetry, dated laminate benchtops, white ceramic tile splashback, and all floor coverings removed throughout kitchen and step-down dining area
  • Split-level floor remediated — the step-down between kitchen and dining area was levelled to create a single continuous floor plane across the open-plan space
  • New custom two-tone cabinetry — white shaker-profile lower cabinetry with brushed brass/gold bar-pull handles throughout; tall dark charcoal full-height upper cabinetry reaching ceiling height; full-height charcoal fridge surround column integrated into the design
  • White Calacatta marble-look stone benchtop — island bench and perimeter in matching white stone; clean waterfall-edge island
  • Grey/silver geometric herringbone marble mosaic splashback — tile panel behind perimeter bench, adding texture and movement to the white cabinetry wall
  • Gold wall-mount pot filler tap on perimeter bench above cooktop — functional detail that reinforces the gold accent palette
  • Induction cooktop on perimeter bench replacing original gas cooktop
  • Black stainless french-door fridge retained within new charcoal surround cabinetry — existing appliance integrated seamlessly into new design
  • Four large globe pendant lights in brushed gold finish — hung above island bench, defining the kitchen zone within the open-plan space
  • Herringbone engineered timber hybrid floor — warm medium-toned timber, laid in herringbone pattern, running continuously from kitchen through dining into living room and out to the alfresco deck
  • Plumbing — kitchen sink and dishwasher connections by licensed Perth plumber; Certificate of Compliance issued
  • Electrical — cooktop circuit, dishwasher circuit, pendant lighting, LED downlights by licensed electrician; Certificate of Compliance issued

Living Room — Structural & Fit-Out

  • Structural wall removal — openings cut through external brick wall to create direct connection between living room and alfresco entertaining area; structural assessment conducted, lintels and post supports installed
  • New skylights — pyramid-profile fully glazed skylight installed in living room ceiling, flooding the large open-plan space with natural light from above; significant structural and roofing work required for installation
  • Full wall preparation and replastering — all walls stripped, repaired, and replastered to smooth finish throughout living room and connecting areas
  • New sliding aluminium-framed glass doors installed in structural openings — connecting living room to garden and alfresco; large sliding door format maximising indoor-outdoor visual connection
  • Herringbone engineered timber hybrid floor continuous from kitchen — same floor running through the full living space without interruption, creating a single open-plan floor plane
  • White panel doors, white architraves, and new skirtings throughout
  • LED downlights throughout living area by licensed electrician
  • Full interior repaint — white throughout living room, hallways, and connecting spaces

Alfresco & Pool

  • Alfresco pergola structure fully repainted white — all posts, beams, and Colorbond roof sheeting repainted in crisp white, transforming the visual weight of the existing structure
  • New large 6-blade ceiling fan in gunmetal finish — replacing original aged fan
  • Festoon/fairy lights strung across pergola ceiling — creating evening ambiance without structural modification
  • Herringbone timber-look deck tiles laid on alfresco floor — matching the interior herringbone floor, creating visual continuity between inside and outside
  • Glass pool fencing installed — frameless glass panels replacing original net fence, opening the visual connection between alfresco and pool
  • Pool resurfacing — pool interior resurfaced and refilled; water treatment and commissioning
  • Tropical planting — bird of paradise, potted plants, and garden refresh around pool and alfresco perimeter

After Photographs

The Challenge

This project should have taken four months. It took twelve. The renovation itself — the structural work, the kitchen, the alfresco, the floor — is all excellent. The extended timeline had nothing to do with the quality of the work or the complexity of the build. It had to do with communication.

In a renovation of this scale, decisions need to be made at specific points in the build sequence. The kitchen cabinetry cannot be manufactured until the design is finalised and signed off. The floor cannot be laid until the layout decisions that affect it are confirmed. The alfresco structure cannot be completed until the materials are approved. Each decision is a gate — and when the client is slow to respond to questions, slow to approve selections, or unavailable for the decisions that need to be made before the next trade can start, every gate creates a delay.

That is what happened here. The client was genuinely difficult to reach throughout the project. Decisions that should have taken two or three days to turn around were taking two or three weeks. In some cases, trades that had been booked and were ready to start had to be rescheduled because the preceding decision hadn’t been made — and in Perth’s 2025 and 2026 trade market, rescheduling a licensed trade means waiting for the next available slot, not the following Monday

The total delay from client communication: approximately eight months added to a four-month project. The renovation itself ran on schedule every time it was running. The gaps between active construction periods were almost entirely attributable to pending decisions.

The result was still delivered. The $500,000 value uplift was still achieved. The owner moved in. But the twelve months of holding costs — mortgage, rates, insurance on a property that could have been occupied eight months earlier — was a real cost that the extended timeline created.

What every homeowner can take from this

A renovation is not just a construction project. It is a collaboration between the client and the renovation company. The company manages the trades, the schedule, and the quality. The client manages their decisions. When one side of that collaboration is consistently slower than the schedule requires, the project extends — and that extension has costs that fall on both sides.

If you are planning a renovation — particularly a full house renovation where decisions compound — be realistic about your own availability. House & Co will give you a clear decision schedule at the start of every project: what needs to be confirmed and when. The timeline we quote is achievable when decisions arrive on time. Every week of delay in a decision is, typically, more than a week added to the project completion date

The Result

The photographs answer the question of whether the result was worth it. The kitchen is one of the most considered in any House & Co project — the two-tone dark and white cabinetry with brushed gold hardware, the herringbone mosaic splashback, the gold globe pendants, and the split-level floor remediated to a single continuous plane. It is a kitchen that was designed and built to a clear vision, even if arriving at that vision took longer than it should have.

The living room skylight is the structural decision that defines the space. The before photograph shows a room stripped to the slab with raw brick openings where walls were being demolished. The after photograph shows a room flooded with light from a large pyramid-profile skylight overhead, herringbone floor running wall to wall, and bifold doors opening to the garden and alfresco beyond. The scale of the structural work involved in that transformation is visible only if you know what you’re looking for.

The alfresco and pool tell the simplest before-and-after story of the three rooms shown. The same pergola structure — same footprint, same roof profile — painted white, fitted with a modern fan, strung with festoon lights, and opened to a resurfaced pool behind glass fencing. The herringbone deck tiles connecting the indoor floor to the outdoor space are the detail that makes it feel intentional rather than coincidental.

Approximate value uplift: $500,000. The owner moved in at the end of twelve months. The home they moved into is exactly what was designed at the start of the project — which is also exactly what a fixed-scope quote is meant to deliver, regardless of how long the journey to get there takes.

Client Review

What the Client Said

Group 20

“I know I wasn’t the easiest client when it came to making decisions quickly. I’ll own that. But House & Co were patient throughout, never dropped the quality of the work, and what they delivered in the end is everything I wanted. The kitchen is spectacular. The living room with the skylight is a completely different house to what I bought. I’d use them again.”

Property owner · Dianella · Full House Renovation

Project Details

About Project

Details

Suburb

Dianella, WA

Project type

Full House Renovation

Home age & type

Owner-occupier — pre-1990, brick

Design style

Contemporary

Rooms renovated

Kitchen · Living room · Alfresco & pool · Throughout

Structural work

Wall removal (living to alfresco) · Skylight installation · Split-level floor remediated

Key design thread

Herringbone engineered timber floor — kitchen to living to alfresco deck

On-site duration

12 months

Cause of timeline

Client decision delays — not construction complexity

Asbestos managed

No — none identified

Replumbing

No — existing plumbing compliant

Delivered to scope

Yes ✓ — fixed-scope quote honoured

Compliance certs

Electrical + Plumbing

Related Projects

Full-house
Inglewood
Derelict to liveable - 10 skip bins cleared - $500K uplift

Full House Renovation — Inglewood

Card teaser A derelict Inglewood property requiring 10 skip bins of clearance before renovation could begin. Full re-render in white, all terracotta roof tiles replaced with charcoal, carport converted to enclosed garage, contemporary two-tone kitchen, sunroom opened to garden with bifold glass doors. Clean property underneath — $500,000 uplift, delivered on schedule.
Roof icon
Contemporary
(1950s, rendered brick — hipped roofline)
Vector (32)
4 months
(18 weeks including design and booking)
solar_dollar-outline
~$500,000 value uplift
Asbestos managed: No — clean property
Replumbing: No — existing plumbing serviceable
Delivered on schedule: Yes
Vector
Electrical + Plumbing
Multi
Belmont
Galvanised pipes replaced - Multi-room saving - Investment to owner-occupier

Contemporary Bathroom & Laundry Renovation — Belmont

An investment property transformed for the owner to move into. Concrete-look grey porcelain running through both bathroom and laundry — matched palette, matched timeline, one agreement. Galvanised supply lines identified at consultation and replaced as part of the fixed-scope quote — no surprise variation.
Roof icon
Contemporary
(Investment property — pre-1985, double brick)
Vector (32)
6 weeks
(10 weeks including design and booking)
solar_dollar-outline
Available on request
Asbestos managed: No — none identified
Replumbing: Yes — galvanised steel supply lines replaced (both rooms)
Delivered on schedule: Yes
Vector
Plumbing + Electrical
Full-house
Morley
Full house - Wall removal - Herringbone oak floor

Hamptons Full House Renovation — Morley

A 1970s Morley owner-occupier that needed everything — and got it. Walls removed for open plan, Hamptons kitchen with island bench, master bathroom with freestanding bath and dual vanity, herringbone oak floor throughout, Hamptons laundry, exterior repainted. Clean property, delivered on schedule, approximately $500,000 value uplift.
Roof icon
Hamptons
(Owner-occupier — 1970s, brick veneer)
Vector (32)
4 months
(18 weeks including design and trade booking)
solar_dollar-outline
~$500,000 value uplift
Asbestos managed: No — clean property
Replumbing: No — existing plumbing compliant
Delivered on schedule: Yes
Vector
Plumbing + Electrical

Ready to start your renovation the right way?

We’ll set a clear decision schedule from day one — and tell you honestly what your timeline depends on.